Directs accelerated execution,data reconciliation
Shopian| Nov, 16:District Development Commissioner (DDC) Shopian, Charandeep Singh Monday chaired a comprehensive review meeting of the District Capex Plan 2026–27 to assess the physical and financial progress of ongoing developmental works across the district.
During the meeting, Chief Planning Officer (CPO) Shopian, Mudasir Ahmed presented a detailed sector-wise abstract highlighting the current status of approved works, fund releases and expenditure.
Out of 1,794 approved works under the District Capex Plan 2026–27, 1,268 works (70.7%) have been taken up for execution, while 847 works (47.2%) have been completed till date.
Against a total approved cost of Rs 4,669.54 lakh, an amount of Rs1,640.19 lakh has been released during the current financial year.
Departments have recorded a cumulative expenditure of Rs 378.82 lakh, representing 23.1% utilization of the released funds.
The DDC reviewed the performance of executing agencies including R&B (Shopian and Zainapora), Jal Shakti (PHE), Education, Health & Medical Education, Irrigation, Urban Development (UDD) and Youth Services & Sports.
While R&B Zainapora achieved 100% utilization of released funds and Education recorded 68.6%, the DDC expressed concern over slow expenditure in sectors like PHE (6.3%) and Youth Services & Sports (0%).
Taking serious note of lagging expenditure in certain departments, the District Development Commissioner directed all sectoral and executing officers to expedite the tendering and execution process to ensure 100% physical completion and optimal utilization of released funds well within the stipulated timeframe.
Emphasizing financial accuracy and transparency, the DDC instructed the concerned departments particularly KPDCL and engineering wings to reconcile discrepancies in annual allocation figures and ensure strict alignment between physical reporting and financial abstracts prior to final certification.
Officers were further directed to maintain strict quality control on ground and conduct regular field inspections to remove bottlenecks hindering project completion.
The meeting was attended by Executive Engineers of R&B, PHE, Irrigation and KPDCL, Chief Education Officer, Chief Medical Officer and other district and sectoral officers.