Srinagar: According to the Power Controller, Kashmir Province, PDD Srinagar, in order to carry out necessary maintenance work, the power supply from Baramulla Ist, Baramulla IInd and Malpora (Nowshera) receiving stations shall remain affected on November 27 from 9 am to 5 pm.
Similarly, power supply from Wanpoh-Qazigund receiving stations shall remain affected on November 25 to November 27 from 10 am to 5 pm.
Meanwhile, for carrying out stringing of 220 KV DC Kishenganga-Wagoora overhead transmission line, Ahmadpora-Kunzar and Kunzar-Magam 33KV lines shall remain closed/affected on November 25 from 09 am to 05 pm. While, power supply from the 33 KV line from Pampore-Chadoora would remain affected on November 25 from 11.30 am to 2.30 pm
The power supply to these areas fed from these lines shall remain affected on the said dates and time.